Constructland Indonesia
PRICE OFFERInterior Fit-Out & Renovation

NUDA Left Building — Tan Studio

Turnkey interior renovation & fit-out of the spray-tan studio adjoining NUDA Skin Lab
ActivityInterior renovation & fit-out — civil, MEP, finishes & joinery Offer No.CL-2026-NUDA-TS-01 ProjectTan Studio Renovation (Left Building) Date30 May 2026 LocationBerawa, Canggu, Bali Validity30 days ClientNUDA — Manon & Jules CurrencyIDR (Indonesian Rupiah)
NUDA Tan Studio floor plan — existing vs proposed
Floor plan — existing (48.4 m²) vs proposed (52.5 m²): two spray-tan rooms, retail lobby & forwarded entrance (1:50)
At a glance

1. Project Overview

Constructland (PT Constructland Group Indonesia) offers to deliver the renovation of the NUDA left building into a dedicated Tan Studio as main contractor on a turnkey basis. The works convert the existing ~48.4 m² unit into a ~52.5 m² studio (the entrance is brought forward, adding ~4.1 m²), comprising two spray-tan rooms, a retail and reception lobby, mini changing rooms, a converted shower and the connection through to the existing NUDA space.

Pricing reflects a fully priced Bill of Quantity covering civil works, floors, walls and ceilings, the spray-tan rooms, entrance and retail joinery, plumbing, electrical and lighting, AC and ventilation, furniture and the NUDA connection — supplied and installed. Loose furniture follows the approved renders; spray-tan machines, screens and consumer electronics are Client-supplied (Section 6).

2. Scope Summary & Price

RefSectionAmount (IDR, excl. VAT)
APreliminaries & General — mobilisation, protection of existing areas, site power9,372,500
BDemolition & Site Preparation — front door, old sanitary, disposal, making-good10,695,000
CCivil, Floors, Walls & Ceilings — screed, granite floors, partitions, insulation, paint, ceiling130,617,000
DSpray-Tan Rooms (×2) — microcement walls, floors, curtain partition, lighting & power92,833,750
EDoors, Entrance, Lobby & Retail — entrance door, mirror, sofa, reception, retail displays, signage86,595,000
FPlumbing, Shower & Toilet — convert end-right toilet to shower, fixtures, waterproofing, finishes54,050,000
GElectrical & Lighting — general, accent & mirror lighting, switches, power points38,338,125
HAC & Ventilation — existing AC service, spray-room exhaust, ducting, fresh-air grilles9,315,000
IFurniture, Storage & Accessories — storage cabinet, built-ins, hooks, loose & display pieces40,710,000
JNUDA ↔ Tan Studio Connection — opening works + sliding aluminium door with mirror8,625,000
KTesting, Commissioning & Handover — leak/drainage/function testing, cleaning, handover2,875,000
Subtotal (excl. VAT)484,026,375
VAT — PPN 11%53,242,901
GRAND TOTAL (all-in, VAT inclusive, rounded)537,269,000
This is the recommended base-scope, all-inclusive number. It assumes the lean configuration (curtain spray rooms, storage retained, shower conversion). Optional upgrades in Section 5 are priced separately and added only if you choose them. The full line-item BOQ accompanies this offer as an Excel workbook.

3. Detailed Scope — What's Included

A · Preliminaries & General
  • Mobilisation & demobilisation, including light scaffolding
  • Protection of existing floors, walls, columns & circulation while NUDA next door stays operational
  • Temporary site power for the works
B · Demolition & Site Preparation
  • Remove existing front door, frame & accessories; prepare new forward opening
  • Remove existing end-right toilet, old sanitary & redundant drainage; cap old lines
  • Remove / relocate existing furniture & storage that conflicts with the new layout
  • Debris removal & disposal; patch and make good after demolition
C · Civil, Floors, Walls & Ceilings
  • Build-up of the ~4.1 m² added area at the forwarded entrance (K250 concrete slab)
  • Floor levelling / screed across the ~52.5 m² interior
  • Main floor finish — 60×60 Infinity granite tile
  • Side / entrance semi-permanent partition & changing-room full-wall partition (steel-frame, Jayaboard / Kalsiboard)
  • Rockwool acoustic & thermal insulation inside the new partitions — included
  • Decorative wall finish (Weldon / Dulux Catylac), ceiling finish (Dulux Pentalite), access panels & wet-area waterproofing (Sika)
  • Making-good & refinishing of the retained existing columns
D · Spray-Tan Rooms (×2)
  • Anti-slip granite floors to both rooms (6.9 m² + 7.6 m²)
  • Microcement spray-resistant wall finish — wipe-clean, moisture-tolerant lining
  • Curtain partition with track to each room (base configuration)
  • High-output even lighting package & dedicated spray-equipment power point per room
  • Anti-mould sealant to corners & junctions for easy cleaning
E · Doors, Entrance, Lobby & Retail
  • New forward entrance door — YKK aluminium with clear glass & Dexson hardware
  • Threshold & entrance floor make-good
  • Large gold-framed lobby mirror; terracotta velvet feature sofa
  • Mini reception desk (plywood + HPL Lamitex)
  • Retail displays — bikinis (stainless-gold), tanning products, jewellery showcase
  • Two mini changing rooms with blackout curtains; entrance branding / signage
F · Plumbing, Shower & Toilet
  • Convert the existing end-right toilet into a shower — civil, drainage, plumbing & finishing
  • Paloma shower column, black floor drain & trap; clean & waste piping with testing
  • Shower waterproofing & microcement finish; two shower screens / curtains
  • End-left area retained as storage (base) — pillar cannot be removed
G · Electrical & Lighting
  • Check & isolate existing electrical before works
  • Philips general lighting across lobby, reception, retail & circulation
  • Accent lighting for retail & reception; mirror lighting
  • Schneider switches, dimmers & power points; dedicated power for spray equipment & cashier / POS
H · AC & Ventilation
  • Service & clean existing AC; verify capacity & drain
  • Panasonic exhaust fan to each spray-tan room with ducting to an approved discharge
  • Fresh-air grilles / louvres for air balancing
I · Furniture, Storage & Accessories
  • End-left storage cabinet & built-in reception / retail cabinetry (plywood + HPL Lamitex)
  • Hooks, hangers & towel holders
  • Loose furniture & retail shelving accessories per the approved renders
J · NUDA ↔ Tan Studio Connection &  K · Handover
  • Opening works to connect NUDA and the Tan Studio
  • Sliding aluminium YKK door with mirror (base connection)
  • Plumbing / shower leak, drainage & function testing
  • Construction & deep cleaning, then handover

4. Key Specifications

Material selections carried in the priced BOQ. Final colours, models and sizes are confirmed against the approved design before procurement.

ElementSpecification
Main & spray-room floorsInfinity granite tile 60×60 (anti-slip to spray rooms)
Spray-room & shower wallsMicrocement — seamless, wipe-clean, moisture-tolerant
Wall paintWeldon / Dulux Catylac interior system
CeilingDulux Pentalite
PartitionsJayaboard / Kalsiboard on light-steel frame + Rockwool (Firerock) insulation
Entrance & connection doorsYKK aluminium, clear glass / mirror, Dexson hardware
WaterproofingSika (Top Seal 107 / Sika 107) with fibreglass to wet areas
Shower set & drainagePaloma shower column SCP 1809, Paloma black floor drain / trap
ElectricalSchneider switches, dimmers & power points
LightingPhilips downlights & projectors (3000–3500K)
VentilationPanasonic exhaust fans to spray rooms
Joinery finish18 mm plywood + HPL Lamitex solid

5. Optional Upgrades

Priced add-ons to the base scope. Add any of these and the figure below is added to the Grand Total. All prices exclude VAT (PPN 11% applies on the combined total).

#Optional upgradeNet add (IDR, excl. VAT)
1 Spray rooms  Full-wall partition upgrade — solid anti-damp full-height walls + 2 doors + 2 dedicated AC units, replacing the curtain partition (curtain credited back) +38,812,500
2 Wet area  End-left closet → second toilet / shower — convert the storage area to a toilet/shower with plumbing & finishing (storage credited back); subject to pipe-routing check +15,180,000
3 Alternative  Use existing NUDA toilet — wall-hung toilet tie-in instead of new wet-works, reducing plumbing scope (alternative to building a new toilet) 8,970,000
4 Connection  Wing door with mirror — upgrade the NUDA connection from a sliding door to a YKK aluminium wing door with mirror +1,725,000
5 Equipment  Spray-tan tents (120×120×200 cm) ×2 — supply & place (Client-supplied by default) Price on request

6. Exclusions — Client-Supplied

Unless added as an optional line above, the following are sourced directly by the Client: spray-tan machines, guns, compressors & tents · consumer electronics (TVs, screens, tablets, POS hardware, audio) · loose décor items beyond those listed in Section I · any item not shown in the priced BOQ. Reinstatement of a de-scoped item or a specification change after signature is handled as a written change order.

7. Indicative Programme

Estimated construction duration ~6 weeks from mobilisation, in four overlapping stages. Mobilisation begins on contract signature and receipt of the down payment — no permit wait, as this is an interior fit-out.

Stage 1 — Strip-outDemolition, protection & making-goodWeek 1
Stage 2 — Civil & MEPPartitions, floors, plumbing & electrical first-fixWeeks 2–3
Stage 3 — FinishesMicrocement, paint, tiling & ceilingsWeeks 3–5
Stage 4 — Fit-out & handoverJoinery, fixtures, testing & cleaningWeeks 5–6
Programme is indicative and subject to site conditions, confirmation of the optional choices, and timely Client decisions on materials, colours and any Client-supplied items.

8. Payment Plan

#Milestone%Amount (IDR, incl. VAT)
1Down Payment on signed contract — mobilisation, site set-up & procurement30%161,180,700
2Mid-build — certified against works verified on site (joint inspection)30%161,180,700
3Handover — on practical completion & cleaning30%161,180,700
4Retention release — at the end of the 90-day Defects Liability Period10%53,726,900
TOTAL (VAT inclusive)537,269,000
A 5% retention is held within the final payment and released on Final Acceptance at the end of the 90-day Defects Liability Period. Optional upgrades, once selected, are added pro-rata across the milestones.

9. Assumptions & Verification

  1. Areas are taken from the proposed floor plan (existing 48.4 m², proposed 52.5 m²). Wall and ceiling quantities assume a 3.0 m height pending site measurement; final quantities are confirmed at shop-drawing / site-survey stage.
  2. Existing columns / pillars are retained (not demolished) and only made good and refinished.
  3. Drainage and pipe routing for the converted shower (and the optional second wet area) are subject to verification of existing services on site.
  4. Where measured quantities differ materially from these assumptions, the affected lines are reconciled by joint measurement before that work proceeds.

10. Terms & Conditions

  1. Prices are in Indonesian Rupiah (IDR). Section 2 amounts are exclusive of VAT; PPN 11% is added once on the combined subtotal. The Grand Total is VAT-inclusive.
  2. This offer covers the recommended base scope. Optional upgrades (Section 5) are priced separately and added only on written confirmation.
  3. Final colours, models, sizes and Client-supplied items are confirmed before procurement. Specification or scope changes after signature are handled as written change orders.
  4. The programme is indicative and subject to permits not being required, site conditions, and timely Client decisions.
  5. This offer is valid for 30 days from the date of issue. Final scope, specification and payment terms are confirmed on contract signature.
For and on behalf of
PT CONSTRUCTLAND GROUP INDONESIA
Ragnar Kenk — Construction Director

Date: __________________
Accepted for and on behalf of
NUDA
Name: __________________

Date: __________________